Schedule for Advanced Mobile and Distributed Systems
Below you'll find the (yet incomplete)
schedule for the course. Note that it may be subjet for change!
The lectures takes place in roome 3A18 typically from 10-12. In
the afternoon (from week 2 and onwards) we may proceed in room 3A18
and from 13-15 the pc-room 3A54 is reserved.
In the schedule below the weeks marked with "project" as the
topic (week 9 and onwards) are devoted to the project work of the
course. One day in week 7 is for presenting project ideas (and consolidate groups) and one
day in week 8 is for each project group to defend and get feedback on
its project ideas.
Two out of three topics of the course have been preselected, they
are Mobile Ad Hoc Networks (MANETs) and Peer-to-Peer (P2P)
systems. A third topic should be decided upon by You in week 3. The
candidates for the elective topic are:
- Bluetooth Scatternets
Test of mobile and distributed software
P2P MMOG middleware
20.09.2007: Bluetooth Scatternets has been chosen as the
elective topic.
|
Week
|
Date
|
Time
|
Room
|
Topic/Slides
|
Reading (Presenter/Opponent)
|
Teacher
|
|
1
|
28/08
|
10-12
|
3A18
|
Introduction/MANETs
|
[MANETs], until p. 255
[DSDV]
|
JCG
|
|
1
|
30/08
|
10-12
|
3A18
|
P2P Intro, Pastry, Tapestry, Common API. Questions
|
[CDK, pp. 397–429]
[Rowstron & Druschel, 2001a]
[Dabek et al.]
Practical exercise (optional)
|
AJG
|
|
2
|
04/09
|
10-12
|
3A18
|
P2P Applications
|
[Druschel & Rowstron] (3/7)
[Rowstron & Druschel, 2001b] (4/8)
[Iyer et al.] (5/9)
|
AJG
|
|
2
|
06/09
|
10-12
|
3A18
|
P2P Evaluation of real applications
|
[Haeberlen et al.] (1/3)
[Castro et al., 2002a] (2/4)
[Castro et al., 2005] (6/5)
|
AJG
|
|
3
|
11/09
|
10-12
|
3A18
|
MANETs, DSR slides
|
[AODV] (7/1)
[DSR] (8/2)
[OLSR] (9/6).
|
JCG
|
|
3
|
13/09
|
10-12
|
3A18
|
P2P Byzantine problems
|
[Castro et al., 2002b] (3/7)
[Fedotova & Veltri] (4/8)
[Pathak & Liviu] (5/9)
|
AJG
|
|
4
|
18/09
|
10-12
|
3A18
|
Uppaal,
Uppaal examples,
presentation of elective topic
|
[Uppaal2K]
[Uppaal] (skip 4.2-4)
|
JCG
|
|
4
|
20/09
|
10-12
|
3A18
|
P2P Overlay networks, choice of elective topic. Exercises
|
[Lua et al.] (1/3)
[Traversat et al., 2003] (2/4)
[Antoniu et al.] (6/5)
(supplemental: [Aberer et al.])
|
AJG
|
|
5
|
25/09
|
10-12
|
3A18
|
Verification
Exercise,
Solution proposal,
Verification Summary
|
[Wibling et al. 1] (7/1). Focus on Uppaal, not SPIN.
[Wibling et al. 2] (8/2)
[Chiyangwa et al.] (9/6). Skim "Establishing refinement ..." p. 312-313.
|
JCG
|
|
5
|
27/09
|
10-12
|
3A18
|
Bluetooth Scatternets, introductory lecture
|
[Whitaker et al.]
|
SD
|
|
6
|
02/10
|
10-12
|
3A18
|
Multi-cast Routing, Secure Routing, and Geocast Routing in MANETs
,
Exercise,
Solution proposal,
Multicast and Secure Routing Summary
|
[Perkins et al.](3/7)
[Sanzgiri et al.] (4/8)
[Chen et al.] (will not be presented)
|
JCG
|
|
6
|
04/10
|
10-12
|
3A18
|
Bluetooth Scatternets
|
[Lee et. al., 2005] (1/3)
[Li & Hwang, 2005] (2/4)
|
SD
|
|
7
|
09/10
|
10-12
|
3A18
|
Bluetooth Scatternets
|
[Madsen et. al., 2005] (6/5)
[Tekkalmaz et. al., 2005] (7/1)
|
SD
|
|
7
|
11/10
|
10-12
|
3A18
|
Project proposals
|
|
JCG
|
|
|
15-19/10
|
|
|
Vacation
|
|
|
|
8
|
23/10
|
10-12
|
3A18
|
Bluetooth Scatternets, slides for [Sreenivas & Ali]
|
[Sreenivas & Ali] (8/2)
[Hodge et. al., 2006] (9/6)
[Peerson et al.] (3/7)
|
SD
|
|
8
|
25/10
|
10-12
|
3A18
|
Defend project ideas
|
|
SD/AJG/JCG
|
|
9
|
29/10-02/11
|
|
|
Project
|
|
|
|
10
|
05-09/11
|
|
|
Project
|
|
|
|
11
|
12-16/11
|
|
|
Project
|
|
|
|
12
|
19-23/11
|
|
|
Project
|
|
|
|
13
|
26-30/11
|
|
|
Project
|
|
|
|
14
|
03-07/12
|
|
|
Project
|
|
|
|
14
|
06/12
|
10-12
|
3A18
|
Rounding off and presenting exam plan
|
Exam plan
|
JCG
|
Presenters and Opponents Groups
| # | Students |
| 1 | Eric, Bjørge, Jørgen |
| 2 | Henning, Eivind, Niccolo |
| 3 | Michal, Qingwei |
| 4 | Frederik, Arnar, Michael |
| 5 | Jakob, Nikolaj |
| 6 | Zhongyuan, Vytautas, Kwame |
| 7 | Martin W, Dirk |
| 8 | Mohammed, Mirko |
| 9 | Wassan, Martin H E, Kremeha |
|